Equations and Variables in the ATB
Calculated Variables Equations
Levelized Cost of Energy (LCOE): Levelized Cost of Energy is a summary metric that combines the primary technology cost and performance parameters: capital expenditures, operations expenditures, and capacity factor.
$$ LCOE = \frac{FCR \times CAPEX + FOM}{CF \times 8,760 (hours/yr)} + VOM + FUEL $$
Fixed Charge Rate (FCR): Amount of revenue per dollar of investment required that must be collected annually from customers to pay the carrying charges on that investment.
$$ FCR = CRF \times ProFinFactor $$
Capital Expenditures (CAPEX): Capital expenditures required to achieve commercial operation of the generation plant.
$$ CAPEX = ConFinFactor \times (OCC + GCC) $$
Capital Recovery Factor (CRF): The ratio of a constant annuity to the present value of receiving that annuity for a given length of time.
$$ CRF = WACC \times \left [ \frac{1}{\left ( 1 - \frac{1}{(1 + WACC)^{t}} \right )} \right ] $$
Weighted Average Cost of Capital (WACC): The average expected rate that is paid to finance assets.
$$ WACC = \frac{1 + [1-DF]\times[(1+RROE)(1+i)-1] + DF\times[(1+IR)(1+i)-1]\times[1-TR]}{1+i}-1 $$
Project Finance Factor (ProFinFactor): Technology-specific financial multiplier to account for any applicable differences in depreciation schedule and tax policies.
$$ ProFinFactor = \frac {(1 - TR \times PVD)} {(1 - TR)} $$
Construction Finance Factor (ConFinFactor): Portion of all-in capital cost associated with construction period financing.
$$ ConFinFactor = \sum_{y=0}^{y=C-1} FC_{y} \times AI_{y} $$
Accumulated Interest (AI)
$$ AI_{y} = 1 + (1 - TR) \times [(1 + IDC)(year + 0.5) -1] $$
Total Battery System Cost
$$ TotalBatterySystemCost($) = TotalBatteryStorageCost($) + TotalBatteryPowerCost($) $$
$$ TotalBatteryStorageCost($) = BatteryStorageCapacity(kWh) \times BatteryEnergyCost($/kWh) $$
$$ TotalBatteryPowerCost($) = BatteryPowerCapcity(kW) \times BatteryPowerCost($/kW) + BatteryPowerConstant($) $$
Total Utility-Scale PV Plu Battery System Cost
$$ PVPlusBatterySystemCost($/MWh) = FixedCosts($/MWh) + VOM($/MWh) + ChargingCosts($/MWh) $$
$$ FixedCosts = \frac {[AnnualPVSystemCost + AnnualBatterySystemCost + FOM($/kW-yr)]\times 1,000(kW/MW)}{CF\times 8,760(hours/yr)} $$
$$ AnnualPVSystemCost($/kW) = RROE \times PFF(PV) \times ConFinFactor \times [ PVSystemCost($/kW) \times 1 + GCC($/kW)] $$
$$ AnnualBatterySystemCost($/kW) = RROE \times PFF(Battery) \times ConFinFactor \times BatteryStorageCost($/kW) \times 1 $$
Input Variables
Input Variable Equations
Depreciation Factor (DepFac): The depreciation factor is a function of the discount rate.
$$ DepFac = \frac {1}{[(1+WACC) \times (1 + i)]^{y}} $$
Real Interest Rate (IR): Assumed interest rate on debt.
$$ IR = \frac {1 +d}{1 + i} -1 $$
Present Value of Depreciation (PVD): PVD is a function of FD, f, and y.
$$ PVD = \sum (MACRS~DF) \times \frac {1}{[(1 + WACC) \times (1 + i)]^{y}} $$
Other Input Variables
Input Variable | Value | Definition/Description |
---|---|---|
Construction duration (C) | Varies by technology | Number of years in construction period |
Capacity factor (CF) | Varies by technology | Generally, the ratio of actual annual output to output at rated capacity for an entire year |
Nominal debt rate (d) | Varies by technology | The nominal debt rate varies by technology. It is fixed over time for the R&D financials, and varies with time in the Markets & Policies financials. |
Debt fraction (DF) | Varies by technology | Fraction of capital financed with debt; 1-DF is assumed financed with equity. |
Expected market return on premium (EMRF) | Varies by technology | The difference between the expected return on a market portfolio and the risk-free rate |
Capital fraction (FC) | Varies by technology | Fraction of capital spent in each year of construction, 1 to C |
Depreciation fraction (FD) | Varies by technology | Fraction of capital depreciated in each year, 1 to M |
Fixed operation and maintenance expenses (FOM) | ATB input ($/MW-year) | Annual expenditures to operate and maintain equipment that are not incurred on a per-unit-energy basis |
Fuel | Heat rate (MMBtu/MWh) *Fuel Costs($/MMBtu) | Fuel costs, converted to $/MWh, using heat rates |
Grid connection costs (GCC) | Varies by technology ($/kW) | Overnight capital cost includes a nominal-distance spur line (<1 mi) for all technologies, and for offshore wind it includes export cable and construction-period transit costs for a 30-km distance from shore. Project-specific costs lines that are based on distance to existing transmission are not included. |
Inflation rate (i) | 2.5% | Assumed inflation rate based on historical data |
Interest during construction (IDC) | Varies by technology | Assumed nominal interest rate during project construction |
Depreciation period (M) | Varies by technology (years) | Number of years in modified accelerated cost recovery system (MACRS ) depreciation schedule |
Overnight capital costs (OCC) | Varies by technology ($/kW) | Capital expenditures if plant could be constructed overnight (i.e., excludes construction period financing); includes on-site electrical equipment (e.g., switchyard), a nominal-distance spur line (<1 mi), and necessary upgrades at a transmission substation |
Capital regional multiplier (CapRegMult) | 1 | Multiplier to account for regional variation in capital costs; not used in the ATB |
Rate of return on equity (RROE) | Varies by technology | Assumed rate of return on the share of assets financed with equity |
Economic lifetime (t) or cost recovery period | 30 years (default); 20 years and technical life also available | Length of time for paying off assets |
Tax rate (TR) | 25.7% | Combined assumed marginal state and federal tax rate before application of available federal tax credits for renewable generators |
Variable operation and maintenance (VOM) | Varies by technology ($/MWh) | Operation and maintenance costs incurred on a per-unit-energy basis |
Year index (y) | — | — |
Assumptions common to all technologies include the following:
- Variables are defined in the Financial Definitions worksheet in the ATB data spreadsheet, where two sets of financial assumptions are available in (1) the R&D Only Financial Assumptions Case (R&D Only Case) and (2) the Market + Policies Financial Assumptions Case (Market + Policies Case).
- Though the tax rate has been updated to include the changes in corporate taxes in the Market + Policies Case, the federal/state blended tax rate is not assumed to vary by technology in our calculations; in practice, depreciation schedules vary by technology based on the tax code.